Interior Demolition Project at radford University

  • PROJECT Washington Hall PROJECT Washington Hall
  • PROJECT interior demolition & Asbestos removal PROJECT interior demolition & Asbestos removal

Client Comment

“It went really smooth. They required minimal supervision to ensure damage didn’t occur to other aspects of the campus. They brought in additional supervision to make sure things moved along well, kept a very clean job site and communicated proactively about timing and staffing. They were just really easy to work with.”
Paul Ely, Project Manager, Radford University

PROJECT STATS

  • Nearly 10,000 man hours in 19 weeks
  • Removed 110,000 sf of plaster ceiling
  • Removed 45,000 sf of vinyl floor tile
  • Removed 17,000 sf of ceramic floor tiles
  • Removed 176,000 sf of block wall
  • Removed 8,300 lights and 18,000 lbs of plumbing and mechanical fixtures
  • Removed 6,000 sf of asbestos floor tile
  • Removed over 500 asbestos plumbing fittings
  • Complex demolition project completed under a tight timeframe with exceptional results

About this PROJECT.

Washington Hall at Radford University (RU) is an old dormitory that contained asbestos materials and lead paint. RU decided to completely gut the building for new electrical, mechanical and plumbing systems. Waco was awarded the contract to demolish the interior of the building, remove hazardous materials, complete LEED requirements for waste recycling, and prep the building for subsequent contractor groups coming in for re-development.

What IT TOOK TO ACHIEVE THIS PROJECT.

Unique Project Challenges

1.Timeframe for completion was very tight considering the scope of the project, and this required exceptional project management skills to ensure multiple teams working simultaneously to accomplish all requirements
2.There were significant LEED requirements for segregation of the waste for recycling

Why WACO was chosen

Price, Expertise and Past success
  • Waco was the low bid on this publicly advertised bid project. Waco’s experienced and knowledgeable estimators were able to put together a bid package that was complete, comprehensive and ultimately was the lowest responsive bid to the University for the project.
  • RU benefited by contracting with a company that already had a state (VASCUPP) contract for hazardous materials removal, and experience working on college campuses
  • RU was confident with Waco’s documentation procedures and knew they would be successful dealing with the project’s unique administrative and logistical challenges
  • RU knew Waco could form the necessary relationships with the Facilities and Capital departments in order to achieve maximum cooperation and productivity
  • RU was convinced Waco had the capital and human resources, and the project management expertise to complete the project in a tight timeframe
  • RU could trust Waco to protect the university’s capital assets and be a responsible steward to the owners

Summary of Results

The project was completed on-time and on-budget, and exceeded RU’s original expectations. Tim Cundiff was the Project Manager from Waco. There was only one change order, which was unforeseen at the beginning of the project and discoverable only after demolition began. Waco’s recycling efforts achieved 95%, which awarded an extra LEED point to the university.

This project demonstrates Waco’s vast knowledge in many critical areas; complex project management through multiple phases and trades, building demolition, asbestos abatement, lead removal, and safety for workers and users. Being one of the largest abatement companies in Virginia, there are few contractors that combine the breadth of technical skills with the ability to manage complex projects to meet owners’ quality and economic requirements.

Contact Waco at 888-822-7285 for more information.

Download a PDF of this Project

Contact Us